Fink Road Landfill Gas Collection and Control System Improvements
Status
Bidding Closed
Prebid Date2/6/19 10:00am
Bid Date3/6/19 2:00pm
Company & Contacts
The work to be accomplished includes the installation of 33 vertical gas wells, (approximately 2,000 feet of vertical drilling), 14 horizontal gas collectors (approximately 3,800 linear feet), and the installation of four (4) pneumatic pumps/sumps and air/condensate discharge lines to be tied into the existing flare station piping. In addition, the Project will involve connecting lateral piping and installing header lines (approximately 3,500 linear feet), to be tied into the existing main header near the landfill gas flare station, as well as a replacement air compressor in the flare station to handle the additional pneumatic load. These new wells and horizontal collectors will be networked to the existing GCCS on Landfill Unit #1; the closed portion of the landfill, and as further presented in the Construction Plans and Specifications